Hot line for investors

+7 861 251 77 64 econom_eisk@mail.ru

The second phase of the construction of the general transshipment complex LLC “KGS-MALL” is still in progress at the port Temryuk

CJSC "Kubangruzservice" is implementing the investment project.

As of today, the berth No.9 – the first phase of the project implementation – has been put into operation. The second phase of the construction, namely, the berth No.8, is under way now. The backfilling of the berth, foundation soil stabilization, manufacturing and installation of piles and other works are in progress.

It is expected that by reaching the projected capacity the transshipment of cargoes, containers, metals, timber and other general cargoes will amount to 300 thousand tons per year.

Cumulative investment amount to be contributed into the project exceeds 1 billion rubles. It is expected to put the facility into operation as early as this year. 253 workplaces, of which 35 were already organized, will be subsequently created.

Source - Investment portal of Krasnodar region